“At Vantage, we share our customers’ commitment to sustainability and being good corporate citizens. We are laser-focused on designing and building our data centers responsibly and sustainably as we expand across North America.” Ryan Dorsett, Principal Construction Manager, Vantage Data Centers
1. General Construction Information
- Schedule: Construction started 3/27/18 and projected to be completed with Integrated Systems Testing (IST) Commissioning by 2/15/19.
2. Site Information
- VA11 Overall Square Footage: 256,256 SF
- VA11 Total Critical Load: 30MW (Building); 6MW (Phase I) – MW – megawatts
- Total campus will be 142MW.
3. Manpower Information
- Total field hours for the job: 254,000 hrs
- Total Peak Manpower: 400 workers
- Electrical Contractor Peak Manpower: 120 workers
- Mechanical Peak Manpower: 60 workers
4. Safety Information
- Bi-Weekly Safety Stand-downs to bring awareness to various safety topics:
- Cranes Safety
- Fall Protection Safety
- Ladder Safety
- Lift Safety
- Electrical Arc Flash Awareness Training Sitewide provided to all workers